Overall Performance Index — All 6 Jurisdictions
Cost Accuracy Index · Delivery Accuracy Index · Combined Score (50/50 weighting) — calculated from officially published outturn data only. ⚠️-flagged indicative estimates excluded from index calculation.
| Rank | Jurisdiction | Cost Accuracy Index | Delivery Accuracy Index | Combined Score | Schemes Tracked | Data Quality Note |
|---|---|---|---|---|---|---|
| 1 | 🇦🇺Australia |
79
/100
|
10 | Good outturn data. Some TEI allocations vs final costs. Limited completed schemes. | ||
| 2 | 🏴Wales |
80
/100
|
10 | Strong outturn publication record. One scheme under budget. ISG administration noted. | ||
| 3 | 🇮🇪Republic of Ireland |
69
/100
|
10 | ⚠️ Most costs are CIS estimates. Fixed-price D&B limits overruns. Low transparency overall. | ||
| 4 | 🏴Scotland |
60
/100
|
10 | Consistent cost overruns on active projects. Tain 20 months late; Ardrossan 21 months; Beeslack 24+ months. | ||
| 5 | 🏴England |
50
/100
|
10 | ⚠️ SRP still active. Outturn data extremely limited. Programme severely behind nationally (23/524 done). | ||
| 6 | Northern Ireland |
40
/100
|
10 | Strule Campus: +145% cost overrun, 96 months delayed. PPP schools all on budget/time but small scale. |
← scroll tabs →
⚠️ England SRP National Context
The Schools Rebuilding Programme (SRP) announced 500+ schools over 10 years. As of June 2026, approximately 23 of 524 prioritised schools have been completed — far below trajectory. The Delivery Accuracy Index score of 30/100 reflects this systemic national programme delay, not just individual project performance. Most England schemes tracked are still mid-construction with no outturn cost data, hence the Cost Accuracy score is marked data-limited (⚠️).
Index Calculation Methodology
Cost Accuracy Index (0–100)
- Formula: 100 − (% overrun × 2 penalty points per 1%)
- Maximum penalty capped at 60 points (floor = 40)
- Only officially published outturn or current confirmed costs used
- Averaged across all qualifying schemes per jurisdiction
- Underrun schemes score 100 (no bonus above 100)
Delivery Accuracy Index (0–100)
- Formula: 100 − (months delayed × 3 penalty points per month)
- Maximum penalty capped at 70 points (floor = 30)
- On-time completion = 100
- Delay measured from originally announced opening date
- Partial completions assessed on school-opening date
Combined Score
- Equal 50/50 weighting of Cost and Delivery indices
- Reflects balanced importance of budget and programme
- Jurisdictions with limited data carry a data quality caveat
Data Inclusion Rules
- ⚠️ flagged indicative/CIS estimates excluded from index
- Fixed-price D&B contracts treated as 0% overrun if completed
- TEI allocations vs final outturn noted where TEI is the basis
- Schemes under construction use current confirmed estimates